PEM replacement...
#7
(22-Aug-2015, 18:02)Manoet Wrote: Got the Furutech Rhodium-plated/pure alpha copper blades IEC module installed this morning to replace the OEM Power Entry Module (sitting beside it in pic). No surprises here. Just open up the OEM cutout by 2mm at left side so flange doesn't partially cover LED at right in pic (cut-out height is perfect as-is) then drill & tap two M3X.5mm holes to accept the Titanium screws I cut short to fit this part. Then install. Total cake-walk project!

Nice work and thanks for the photos!  

Question - what is the prefered means of getting the schurter pem out of the chassis opening?  I see the spring retaining tangs.  Do you just compress them with channel locks?

Thx
Kenreau
Synology DS412+> Aurender S10> AQ Wel AES > Devialet 200> AQ Castle Rock Bi-Wired > Vandersteen 5As.
Reply


Messages In This Thread
PEM replacement... - by Manoet - 22-Aug-2015, 18:02
RE: PEM replacement... - by hrky_zmaj - 22-Aug-2015, 20:57
RE: PEM replacement... - by kenreau - 03-Sep-2015, 19:42
RE: PEM replacement... - by Manoet - 22-Aug-2015, 22:39
RE: PEM replacement... - by hrky_zmaj - 22-Aug-2015, 23:04
RE: PEM replacement... - by Manoet - 22-Aug-2015, 23:41
RE: PEM replacement... - by kenreau - 03-Sep-2015, 19:44
RE: PEM replacement... - by Manoet - 05-Sep-2015, 00:36
RE: PEM replacement... - by kenreau - 14-Oct-2015, 16:32
RE: PEM replacement... - by Borgen - 14-Oct-2015, 17:26
RE: PEM replacement... - by Confused - 14-Oct-2015, 19:27
RE: PEM replacement... - by Borgen - 14-Oct-2015, 19:45
RE: PEM replacement... - by Manoet - 14-Oct-2015, 20:29
RE: PEM replacement... - by kenreau - 14-Oct-2015, 23:40
RE: PEM replacement... - by mauidan - 15-Oct-2015, 05:21
RE: PEM replacement... - by Manoet - 15-Oct-2015, 08:49